Atyrau Region, 19 November. Construction of a gas processing plant with a capacity of 1 billion cubic metres a year at the Kashagan field is 65.12% complete under the EPC contract.
Construction, installation and commissioning work is 48.53% complete. The figures were given by the national company QazaqGaz, which reported a working trip to the site by its management and representatives of NCOC shareholders.
An EPC contract covers design, procurement of equipment and construction. The second figure relates only to work on site, and QazaqGaz does not explain why it is lower than the first.
There are now 1,705 specialists working on site, including 1,127 core staff. Night shifts involve 142 workers, and 314 units of construction equipment are in use. QazaqGaz separately stresses that special attention is paid to occupational safety and industrial safety, including when organising night work.
After inspecting the facility a working meeting was held with the participation of specialists from GPCI LLP and representatives of contractors. The participants reviewed the progress of construction and installation work and discussed which main stages of the project must be completed by the end of the year. The company also says it constantly monitors the project: the approved schedule, quality of work and safety standards. The date for commissioning the plant is not given in the report.
What it means: QazaqGaz named two indicators of the plant’s readiness: almost two thirds under the contract as a whole and less than half for construction and commissioning itself. By the end of the year the company and the NCOC shareholders want to pass the main stages of the project.
Background: NCOC (North Caspian Operating Company) is the operator of the Kashagan project.