Energy ministry: two more solar plants with 30 MW to start by year-end

Illustrative photo: a solar power plant
Illustrative photo. Source: Hp.Baumeler / Wikimedia Commons, CC BY-SA 4.0

Astana, 23 November. Two solar power plants operated by Alkhena LLP with a combined capacity of 30 MW will start operating in the Kyzylorda region before the end of 2026, bringing the year’s total to five solar plants with 92 MW, the Ministry of Energy said.

Three solar plants with 62.6 MW are already running: Stellar Energy with 20 MW in the Mangystau region, Altyn Solar Energy with 22.6 MW in the Kostanay region and Jetisu Terra Power with 20 MW in the Zhetysu region. In total, 10 renewable energy facilities with a combined capacity of 245 MW are scheduled for 2026, and seven have already been commissioned, the ministry listed.

Solar still accounts for the smaller part of green energy. The total installed capacity of renewable facilities in the country is 3.7 GW, of which 1.3 GW is solar. In the first nine months of 2026 renewables generated 7.8 billion kWh of electricity, with solar plants contributing 1.9 billion kWh, the ministry said.

The ministry is counting on large projects next. The pipeline of prospective solar projects amounts to about 900 MW, including a 300 MW plant by China Energy and projects by Tumar Commerce totalling up to 1 GW. By the end of 2035 at least 8.4 GW of new renewable capacity is to be commissioned, including about 1.8 GW of solar. The ministry recalls that the President, in his Address, called for special attention to solar generation.

The statement on five plants for the year includes three that are already running and two promised by 31 December, so the ministry has summed up the year five weeks early.

What it means: Solar power in Kazakhstan grows in steps of 20 to 30 MW, while dozens of times more capacity must be added by 2035. The ministry links most of the growth to large projects such as those of China Energy and Tumar Commerce, but gives no commissioning dates.

Who benefits: Renewable energy investors, for whom the state is assembling a project pipeline, and the regions where plants are being built. The statement does not say how the new capacity will affect tariffs.

Background: In October construction began in Kyzylorda of the region’s first solar plant with energy storage.

We have also reported that construction has begun in Kyzylorda of the region’s first solar plant with energy storage.