Almaty CHP-2 gas conversion is 97% complete, soil slows work at CHP-3

First Deputy Prime Minister Nurlybek Nalibayev at a model of the plant while inspecting the modernisation of Almaty’s CHP plants, November 2026
Photo: Press service of the Government of Kazakhstan (primeminister.kz)

Almaty, 28 November, . The project to switch Almaty’s Combined Heat and Power Plant No. 2 (CHP-2) from coal to natural gas is 97% complete, while ground conditions and the dismantling of operating units are complicating site preparation for the second power unit at CHP-3, the Government said.

First Deputy Prime Minister Nurlybek Nalibayev inspected progress at both plants.

At CHP-2, according to the Government, construction and installation work is nearing completion and equipment is being commissioned. Some 1,300 specialists and 83 machines are working on site. Nalibayev was told that full connection of the equipment is scheduled before 25 December and that the modernisation is due to be completed by the end of 2026.

At CHP-3, reconstruction with the installation of combined-cycle gas turbine equipment continues: once it is finished, the plant’s electrical capacity is expected to reach 543.6 MW. More than 1,000 people and 79 machines are working there. During the inspection it was noted that preparing the ground for the second power unit is complicated by the engineering and geological conditions of the soil and the need to dismantle units that are still operating. According to the Government, these factors are affecting the pace of site preparation and preventing a faster move to construction and installation work on the second unit.

Nalibayev ordered that the set deadlines be met and that the work not fall behind schedule. “The project is under the control of the President of the Republic of Kazakhstan. Therefore, it is necessary to monitor the progress of the work and bring it to completion. This is a very important project of special significance for the residents of Almaty,” he said.

Both plants belong to Samruk-Energy, the energy company of the Samruk-Kazyna fund. The statement does not give a timeline for CHP-3.

What it means: The most visible part of the project, converting CHP-2 to gas, is nearly finished, while the second plant has a problem the Government named openly: the soil and old units are holding up construction of the second power unit.

Who benefits: Almaty residents, for whom gas instead of coal at CHP-2 means less smoke in winter. The city’s power system, which needs the new capacity at CHP-3. Samruk-Energy, which the Government expects to meet its deadlines.

Background: CHP-2 is Almaty’s largest coal-fired plant. A Siemens Energy gas turbine was fired up there on 25 November, and the plant is due to deliver its first electricity to the grid on 30 November. Once the switch to gas is complete, emissions of pollutants are expected to fall by more than 90%, according to the Energy Ministry’s estimate.

We have also reported that the first gas turbine was put into operation at Almaty CHP-2.