Astana, 14 November. The Aviation Administration of Kazakhstan has begun certifying the aerodrome of Zaysan airport, which is under construction in the East Kazakhstan Region.
This is one of the final stages of the project, the Ministry of Transport said on 14 November.
The Zaysan and Katon-Karagai airports, both under construction, were visited by the Vice Minister of Transport, Talgat Lastayev, and the deputy akim of the East Kazakhstan Region, Bakhytzhan Baiakhmetov. In Zaysan, the ministry says, the runway, apron, taxiway, access roads and main utility networks have been built. Lighting and radio navigation equipment has been installed. Finishing, installation and commissioning work continues in the airport buildings.
In Katon-Karagai the runway, apron, taxiway and a modular boiler house are ready, and the relocation of a national road has been completed. Utility networks and treatment facilities are still being built there, buildings are being finished and air navigation equipment is being installed. The ministry does not report on the certification of that aerodrome.
Certification is a check that the runway, equipment and services of an aerodrome meet the standards and that it is ready to receive aircraft. The statement does not say how long it will take.
The opening dates of both airports have already been postponed. The commissioning of the airports in Zaysan, Katon-Karagai and Kenderli in the Mangystau Region is planned for May 2027: the Deputy Prime Minister and Minister of National Economy, Serik Zhumangarin, said so at a government meeting on 3 November. Construction in Zaysan was planned to be completed by the end of 2026 and in Katon-Karagai in February 2027, the Kazinform news agency recalls.
The price has changed as well. On 4 November the First Deputy Prime Minister, Nurlybek Nalibayev, put the cost of Zaysan airport at about 68 billion tenge, Katon-Karagai at 89 billion and Kenderli at 69 billion tenge; together that makes 226 billion tenge. In September the state enterprise Kazaeronavigatsia, which is funding the construction, estimated the three projects at about 117.7 billion tenge. These reports do not explain why the estimates differ almost twofold.
What it means: Zaysan airport has moved from construction to inspection: the runway and equipment are ready, and certification is under way. Katon-Karagai is one stage behind. Under the government’s plans, six months remain until the first passengers, and the estimated cost of the three airports has almost doubled over the autumn.
Who benefits: According to Kazinform, the airports are being built to improve transport access to East Kazakhstan and to develop its tourism potential. The construction is paid for by Kazaeronavigatsia; the ministry does not name the contractors in its statement.
Background: Zaysan and Katon-Karagai are districts in the east of the East Kazakhstan Region, near the borders with China and Russia. All three new airports were designed with runways 2,200 metres long and a capacity of up to 150 passengers an hour. The Aviation Administration of Kazakhstan is the organisation that oversees flight safety and certifies aerodromes and airlines.