At the Government Hour in the Kurultai on 23 November several percentages were heard at once, and all of them answered one question: how much Kazakh-made the oil companies buy. The Deputy Speaker gave 21.3%, the Minister of Industry 21%, a deputy 12%, the Deputy Energy Minister 16.4%, and figures of 53, 56 and 65% were heard alongside. There is no contradiction here: each speaker measured his own slice of the same basket. Once the figures are put in their places, a fairly clear picture emerges of why factories complain of empty order books while trillions in purchases go abroad.
Local share in oil purchases
- 2.8 trillion tenge
purchases by TCO, NCOC and KPO in 2025 - 56%
local content in those purchases, including works and services - 74 billion tenge
Kazakh content in the goods they bought - 30%
target share of Kazakh goods at each of the three operators by 2029
According to the Energy Ministry and Kurultai deputies
- 2.8 trillion tenge
One basket, many percentages
In Kazakhstan, local content means the share of Kazakh input in a company’s purchases: the work of Kazakh contractors, the wages of local staff, domestic materials and parts. It covers both what is done by hand and what is bought from a warehouse, so it almost always looks impressive. To see how factories are doing, the goods have to be separated out.
That is what happened at the Government Hour. Deputy Olzhas Nuraldinov called Tengizchevroil, the North Caspian Operating Company (NCOC, the operator of Kashagan) and Karachaganak Petroleum Operating (KPO) the “three whales” of the industry, accounting for about 70% of purchases in the oil and gas sector. According to him, in 2025 these three companies bought goods, works and services worth more than 2.8 trillion tenge, local content reached 56%, but goods accounted directly for only 12%. The same sum, 2.8 trillion tenge, was given in October by the Ministry of Energy too, at an oil and gas engineering forum in Uralsk.
Deputy Energy Minister Yerlan Akbarov gave a more detailed breakdown. “In 2025, for the three whales, goods made up 16.4%. That is about 458 billion tenge. Of this, 74 billion provided local content in goods,” he said. There are three numbers in that sentence, and the meaning is in the last. Goods took about a sixth of all purchases by the three operators, and the Kazakh share of those goods was 74 billion tenge out of 458 billion, also roughly a sixth. Against the total purchases of the three companies, that is less than 3%.
Minister of Industry and Construction Yersaiyn Nagaspayev gave broader figures covering all large oil producers and oil and gas companies. In the first half of the year they bought products worth 2.2 trillion tenge, local content was 53%, and goods accounted for only 21%. “The figure is rather low. And if you take the three whales, the percentage there is even lower,” the minister admitted. Kurultai Deputy Speaker Daniya Yespayeva gave a similar figure, 21.3% for the half-year in the oil and gas sector, and added that solid-minerals subsoil users buy only 17% domestic products, Ulysmedia.kz reported.
The local content of these figures is high: they are all Kazakh, they just cannot be added together.
What is not made at home
The minister explained plainly why there are so few goods. The figures, he said, are pulled down by purchases of complex process equipment for building plants, and Kazakhstan does not yet make some of these products. Some equipment also needs special international certification, which takes time and is not carried out in Kazakhstan. Oil and gas equipment has to withstand hydrogen sulphide, high pressure and high temperature: the Caspian fields are demanding, and a chance supplier will not get into that chain.
Yespayeva sees in this not only technology but habit. “For decades we have continued to buy abroad a basic range of valves, pumps, cables and reagents that we could produce ourselves,” she said. Her list contains neither drilling rigs nor gas processing plants: she is talking about simple items found at any oilfield which, in the Deputy Speaker’s view, local enterprises could make.
She also has a complaint about the accounting itself. The Register of Kazakhstani Producers, she said, still does not distinguish screwdriver assembly from deep processing. For a buyer this means that a plant assembling someone else’s product from imported parts and a plant making it from Kazakh metal can look the same in the register. The Ministry of Industry is now strengthening exactly this register. On 17 November, at a Government meeting, Nagaspayev said that about 2,600 producers and 72,000 product items were registered in it. The ministry intends to use artificial intelligence to check enterprises and monitor the utilisation of their capacity.
A promise instead of an order
To come into being, a plant needs not a one-off contract but confidence that its products will be bought for years. That is what an offtake contract is for: an agreement under which a large buyer undertakes in advance to buy a plant’s output. With such a contract it is easier to get a loan and start a production line.
The offtake figures sound solid. Akbarov said that this year oil and gas companies signed 27 such agreements worth 301 billion tenge. On 17 November the Ministry of Industry gave an even larger set of figures: since 2025 more than 2,500 long-term contracts and 707 offtake contracts have been concluded. In October in Uralsk, according to the Ministry of Energy, the major operators signed contracts with domestic producers worth about 320 billion tenge.
Yespayeva, however, believes that something else often lies behind these numbers. In her words, the offtake contract tool “is often replaced by banal short-term contracts to meet corporate KPIs”, while private business spends years making its way through “labyrinths of procurement procedures”. Following the Government Hour, the deputies recommended that ministries teach banks to accept offtake contracts as collateral, so that a buyer’s promise turns into money for the plant, as we reported earlier in the day.
What they promise to change
The Government is responding to the criticism with several steps. Nagaspayev said that requirements for buyers to purchase domestic products in regulated procurement would be tightened and liability introduced for failing to meet them. The minister did not specify what the penalty would be or whom it would affect. An ecosystem of suppliers is to be built around large enterprises, and a new model of industrial clusters is being developed for cooperation between big and small business.
The second part of the answer concerns special economic zones. Infrastructure in them, the minister said, should be prepared before an investor arrives, and financing of $1.3 billion from the Islamic Development Bank is being studied for this purpose. Management of the zones is to be handed to private companies, including foreign investors, and projects are to be selected with an assessment of the capacity balance, so as not to build plants that duplicate existing ones. This year, according to the minister, 200 projects worth 1.7 trillion tenge are planned, creating more than 17,000 jobs; 130 projects have already been launched.
The Ministry of Energy has its own target. Under the local content development programme, by 2029 the share of Kazakh goods in the purchases of each of the three largest projects should reach 30%. For this year the ministry has identified nine types of goods across 160 items for which domestic production is being specifically built up.
The distance to the goal
The 30% target is worth comparing with what exists. The deputy minister speaks of the share of goods in purchases, and by his own figures goods now account for 16.4% at the three operators. If the target means the share of Kazakh goods in total purchases, the path runs from today’s 74 billion tenge to a sum many times larger. If it means the share within the basket of goods, the path runs from a sixth to a third. None of the reports on the Government Hour says which of the two counts is meant, and this decides whether the growth in question is twofold or tenfold.
The ambiguity is telling. Four speakers at one sitting named four different percentages, and each was right within his own limits. For factories waiting for orders, what matters is not the limits but the result: how many pumps, cables and valves will be bought from them in a year. So far, by that measure, the three main buyers in the industry put together 74 billion tenge out of 2.8 trillion in 2025.