KTZ says the roadbed of the Bakhty–Ayagoz railway line is 93% complete

Machinery on the roadbed of the Bakhty–Ayagoz railway line under construction
Photo: Kazakhstan Temir Zholy (KTZ)

Astana, 13 November. The roadbed of the 303 km Bakhty–Ayagoz railway line is 93% filled: of 39.5 million cubic metres of soil, 36.8 million cubic metres have been laid, the national company Kazakhstan Temir Zholy (KTZ) said on 13 November.

According to the company, construction is on schedule. Most of the remaining work is in the border zone and at Bakhty station. Builders are now levelling the top layer of the roadbed and checking how well the soil has been compacted: after that the laying of the track superstructure — rails, sleepers and fastenings — will begin.

Engineering structures are being built at the same time. Of 267 culverts, 245 are ready and another 15 are under way. Of 19 cattle passes, 12 are ready. Work is in progress on 43 of the 47 bridges. Bridge beams are made directly on site to cut production and delivery times; certification and quality control, the company assures, are carried out in line with building codes.

Track materials are purchased from Kazakh producers. The rails are supplied by the Aktobe Rail and Section Works, the sleepers and fastenings by the partnerships RWS Bindind, Innotrack, Fastenners 2metall and Magnetik, and the turnouts by Prommashkomplekt. The materials are received and distributed near Ayagoz station.

To service the line, KTZ has set an additional staff of 870 specialists. In total the project, according to the company, will create about 1,300 jobs. Construction on the territory of Kazakhstan is planned to be completed at the end of 2027. The company did not say how many kilometres of track have already been laid.

What it means: Construction of the third railway outlet to China has almost passed the earthworks stage and is approaching the laying of rails. Little more than a year remains until the deadline, the end of 2027, and the bridges are still being built: work is under way on 43 of 47.

Who benefits: The line will open a third railway crossing on the border with China, Bakhty–Bokhtu. According to KTZ, it will relieve the Dostyk and Altynkol crossings, which are operating at the limit of their capacity, and support the economy of the Abai Region. Orders have gone to Kazakh plants supplying rails, sleepers and turnouts.

Background: Trains between Kazakhstan and China currently run through two border crossings, Dostyk and Altynkol. The volume of rail freight between the two countries grew by 8% in the first 10 months of 2026, the Ministry of Transport said on 13 November.

We have also reported on how rail freight between Kazakhstan and China grew by 8%.