Nalibayev proposes bringing the Turkestan CCGT plant to full capacity by end-2027

Nurlybek Nalibayev at the Turkestan CCGT construction site, 20 November
Photo: Government of Kazakhstan

Turkestan Region, 20 November. First Deputy Prime Minister Nurlybek Nalibayev, visiting the construction site of the 1,113.4 MW Turkestan combined-cycle gas turbine (CCGT) plant in Sairam District of Turkestan Region, told builders not to let the work drag on and proposed bringing the plant to full capacity by the end of 2027, ahead of schedule.

“Construction must not drag on; the work must be completed within the set deadlines,” Nalibayev said.

Construction and installation work is 62% complete, according to the Government, up from 15% at the start of the year. Power lines are 96% laid, the gas pipeline has been built and a 3.1 km access road commissioned. The site employs 2,455 people: 2,281 on the day shift and 174 at night. Gas and steam turbines and heat-recovery boilers have been delivered, and all four Siemens gas turbine units installed.

Under the schedule, the first unit is to undergo a test start-up by the end of the year, 382 MW is to come on stream in May 2027 and another 382 MW in August, and the plant is to reach 764 MW by September 2027. The remaining stages had been planned for March–May 2028; it is these that Nalibayev proposed bringing forward. Two of the seven wells for process water are working and supply 960 cubic metres a day against the first stage’s need for 240. Judging by the report, the site has water to spare: two wells out of seven yield four times what the first stage needs.

On the same trip Nalibayev inspected the Sastobe chemical complex in Tulkubas District, designed to produce 400,000 tonnes of lime, 100,000 tonnes of caustic soda, 120,000 tonnes of polyvinyl chloride, 200,000 tonnes of calcium carbide and 1 million tonnes of cement a year. The lime line was commissioned last year, and the timing of the next stages has been revised in light of financing; officials were told to find funding and complete the engineering infrastructure.

Ansar Aidarov, Chairman of the Management Board of Samruk-Energo JSC, was also in Turkestan Region on 20 November. In Sauran District he inspected a 300 MW solar power plant with a 90 MW, 360 MWh energy storage system that the company is building with China Energy under an intergovernmental agreement between Kazakhstan and China. All photovoltaic modules and inverters have been mounted, the main transformers and storage equipment installed, and 890 workers and 108 machines are on site; the 220 kV Kentau substation is being expanded and two power lines built to deliver the output. The plant is due to be commissioned in the first quarter of 2027.

What it means: The south of the country is to get a new gas-fired plant of more than a gigawatt and a large solar plant with storage as early as 2027. The Government wants the gas plant’s commissioning not to stretch into 2028.

Who benefits: Neither the Government nor Samruk-Energo says. The new capacity will feed the southern power system, and Nalibayev has proposed shortening the gas plant’s commissioning timeline.

Background: Since late October Samruk-Energo has been headed by Ansar Aidarov, who replaced Kairat Maksutov; he previously led the company’s project office and investments.

We have also reported that two 1 GW wind farms are planned in Kazakhstan by 2029 and that Samruk-Energo head Kairat Maksutov was removed on the day of the State of the Nation Address.