Astana, 25 November. Deputy Prime Minister Kanat Bozumbayev has ordered amendments to the rules of the national project “Modernisation of the Energy and Utilities Sectors” (MEKS) to be prepared by 15 December, the government press service said.
A government resolution on them is to be adopted by the end of the year. In 2027 the national project will continue to renew heating, power and water supply networks; new and ongoing projects will cost 822.6 billion tenge.
The instructions were given at a meeting of the MEKS project office that Bozumbayev chaired on 25 November. According to the government, 366 projects are ready for implementation. Zhetisu Region, West Kazakhstan Region and Almaty Region are spending the national project’s funds most actively.
The amendments grew out of checks on the ground. On the deputy prime minister’s instructions, the project office examined 135 projects in nine regions and proposed three changes. Procurement procedures are to be simplified, more utility companies with badly worn networks involved, and a project’s cost may be revised if expenses have risen for good reason. The Ministry of National Economy and the Committee for the Regulation of Natural Monopolies have been told to go through problems with the regions every week, and project managers to see projects through to commissioning.
The government has also turned to contracts for next year. Tenders are currently under way for 106 projects, and the akimats of Almaty, Almaty Region and Atyrau Region have been told to sign contracts for all projects declared for 2027 by the end of December. “This year we have time to do our homework for the following periods, we must clearly set the rules of the game, use all available digital tools and avoid mistakes,” Bozumbayev said.
The lending rules are changing too. To make it easier for utility companies to borrow, amendments to the subsidy and banking regulation rules have been prepared; financial institutions, according to the press service, are ready to finance approved projects as soon as the amendments take effect. The deputy prime minister ordered registration of the changes to the subsidy rules to be completed within three days.
Another strand of the national project concerns Kazakh manufacturers. More than 3,000 orders for materials and equipment have been placed on the MEKS electronic platform, the government says, and 120 contracts have been signed with domestic enterprises. The Kazakhstan Centre for Modernisation and Development of Housing and Utilities checked 75 projects in 18 regions and found violations of domestic content requirements at 14 sites. Bozumbayev demanded tighter control and economic conditions for manufacturers that take account of their capacity, prices and delivery times.
In 2027 power grids will be rebuilt in seven regions: North Kazakhstan, Akmola, Pavlodar, Karaganda, Turkistan, Mangystau and Atyrau. This will require cable, power line towers and other equipment, so the Ministry of Industry and Construction has been told to publish the regions’ needs for materials for next year by 1 January. The project office will review how the instructions have been carried out at its final meeting in December.
What it means: The government is preparing the next year of the national project in advance. The money for 2027 has been counted and projects selected, while the rules on procurement, price revision and lending are being changed before the new year begins. The deadlines are mid-December for the amendments and the end of the year for the resolution and the contracts.
Who benefits: Utility companies with worn-out networks, which get easier access to projects and loans, and Kazakh plants making cable, towers and equipment: they will be shown in advance how much output the regions will need.
Background: MEKS is a national project to renew heating, power and water supply networks; it is run by a project office chaired by the deputy prime minister. National projects in Kazakhstan are approved by the government, and project offices review progress at regular meetings.