Samruk-Energy plans first power from Almaty CHP-2 to the grid on 30 November

Samruk-Energy and contractor managers at the construction site of the Almaty combined heat and power plants, 25 November 2026
Photo: Samruk-Energy JSC

Almaty, 25 November. At Almaty’s second combined heat and power plant (CHP-2), which is being converted to gas, the third Siemens Energy gas turbine was fired up on 25 November, Samruk-Energy said.

Supply of electricity to the grid is scheduled for 30 November. Ansar Aidarov, chair of the company’s management board, inspected progress at CHP-2 and CHP-3 the same day.

The project under way at CHP-2 is called “Modernisation of Almaty CHP-2 with minimised environmental impact”. Since 31 October the city has been receiving heat from the plant’s new hot-water boiler house. Hot commissioning is now under way, the company says, with three gas turbines and one steam turbine being prepared for phased start-up.

Three weeks ago Energy Minister Yerlan Akkenzhenov named a different milestone: on 4 November he said CHP-2 would be fully launched after conversion to gas on 25 December, with coal kept only as a reserve fuel. Samruk-Energy does not mention a date for full commissioning in its statement: 30 November is the day of the first supply of electricity to the grid.

CHP-3, where combined-cycle units with a total capacity of up to 544 MW are being installed, is still at the assembly stage. Some 95% of the main process equipment has been delivered to the site. Installation of the first Ansaldo Energia gas turbine unit is 69% complete, the first heat recovery boiler 90% and the steam turbine condenser 50%, and the thermal envelope of the main building is 70% closed. The water treatment building, the gas treatment unit with a booster compressor station and the 220 kV and 110 kV switchgear have been completed; equipment is being installed in them.

Following the visit, Aidarov ordered construction and installation work to be accelerated, contractors to be monitored more strictly and capacity to be commissioned on schedule. The company names the goals of both projects: cleaner air, more reliable heat and power and meeting the growing demand of Almaty and Almaty Region.

What it means: The renovated CHP-2 is approaching its first supply of electricity: the new boiler house is already working, and three gas turbines are being brought into operation one by one. CHP-3 is still at the assembly stage, and the company’s head is demanding faster progress.

Who benefits: Almaty residents, for whom gas instead of coal at the two plants means less smoke in winter, and the power system of Almaty and the region, where demand for capacity is growing. Samruk-Energy does not give the cost of the work in its statement.

Background: Aidarov became head of Samruk-Energy on 30 October 2026 after Kairat Maksutov was dismissed: the government explained that dismissal by insufficient control over construction deadlines. Samruk-Energy is part of the Samruk-Kazyna fund.

We have also reported that Almaty CHP-2 was promised to be launched on 25 December and CHP-3 by the end of 2027.